EPLAN ElectricalEngineering
Assembly of MCC electrical cabinets, PLC panel and RIO panel. FAT tests in workshop and commissioning of communications.
Duration: 4 months
Location: Houten, Utrecht, The Netherlands
Assembly of MCC electrical cabinets, PLC panel and RIO panel. FAT tests in workshop and commissioning of communications.
Duration: 4 months
Location: Houten, Utrecht, The Netherlands
Related
Installation and connection of power cables, signal and power trays, equipotential networks; laying and connection of instrumentation signals, As-i network cabling and connection of elements; laying and connection of pneumatic tubing for valve actuation; assembly of pneumatic valve blocks, labelling of cables and electrical testing on site.
Project for the installation of a plant for the reception, storage, blending, and dispatch of palm oil, molasses, and fatty acids in a seaport.